PlasmaTorch
Banned
I disagree, your scenario would yield sufficient HEU for (maybe) one bomb with a second uranium bomb not ready for at least four months[1], so the sequential bombing factor wouldn't be there. The production rate would be far slower than the plutonium route. Historically the uranium path consumed vastly more resources[2]. for far fewer bombs[3].
Thats not quite true. The groves memorandum clearly states that at oak ridges rate of production, they would have a gun type bomb available in august (which they did), and another ready in september. Thats an interval of two months, not four. Your claim doesn't correspond with the rate of uranium enrichment that would have been taking place at oak ridge. In my scenario, they would have a bomb available in march of 1945, and another ready in may.
While its true that oak ridge was more expensive than hanford, one should realize than uranium has certain advantages over plutonium. Reactors consume far more uranium feed than a gaseous diffusion plant or calutron will. Moreover, plutonium can only be utilised by the implosion method, a staggeringly difficult undertaking that required major advances in hydrodynamics and computation. The implosion method wasn't an option in early 1945 because the science still hadn't been worked out.
One reasonable possibility is a HEU implosion design, an idea that wasn't pursued in the Manhattan Project. This would be far more efficient in it's use of HEU and allow for production of four bombs instead of one. Of course pure plutonium or plutonium/HEU composite are even more efficient use of resources.
Actually, the groves memorandum reveals that they were thinking about applying the implosion method towards uranium. After the trinity test validated the concept, it wouldn't take much additional effort to make this happen. I'm not sure what the yield of a uranium implosion bomb would be, though.
Now if the eight months lost in faffing around in the early stages hadn't happened 105-B (the plutonium production reactor) might have been started in JAN1943, been operating in FEB1944 and producing plutonium in May with the "D" and "F" reactors operational in June. So Los Almos would have their first reactor plutonium in JUN1944 and enough to construct a first core for testing in DEC1944 (happy xmas!) with the first four operational MK3 analogues ready for delivery by the end of January 1945.
[1] Historically the first MK1 was available in mid-July of 1945 and the second was projected (for tactical use in support of Downfall) for early December.
[2] Electricity, silver, construction materials and money. Of the $1.9 billion (1945 dollars) cost of the Manhattan Project the Oak Ridge facility consumed $1.2 billion for the uranium separation operation while Hanford (plutonium) cost $390 million. The remainder was: materials ($103 million), Los Almos ($74 million), general R&D ($70 million), heavy water ($27 million) and government administration and overheads ($37 million).
A further breakdown of the Oak Ridge elements is:
K-25 (Gaseous Diffusion) $512 million
Y-12 (Electromagnetic) $478 million
S-50 (Thermal Diffusion) $16 million
Laboratories $27 million
Engineer Works, HQ and central utilities $156 million
[3] Approximately 30-to-1 in fact.
Fair enough, but they would still need to work through the problems with xenon poisoning. Also, was work on the implosion method far enough along that they could even attempt a test like trinity in december of 1944? There were still alot of unknowns at that time, IIRC.
Last edited: