Sir John Valentine Carden survives.

Status
Not open for further replies.
18 April 1938. 10:00hrs. Farnborough, England.
  • 18 April 1938. 10:00hrs. Farnborough, England.

    Vulcan Foundry, despite all the delays due to shortage of components and armour plate, and especially the Wilson epicyclic gearbox, had finally delivered the A12E1 to the MEE for testing. When the mock-up had been looked at the previous year some changes had been suggested, and these were incorporated into the prototype, including the provision of a Close Support howitzer in place of the 2-pdr in some of the tanks.

    The twin AEC diesel engines behaved beautifully during testing, though there were cooling problems that would need to be resolved before the production model could be produced. The six-speed Wilson pre-selector gearbox and Rackham clutches also performed fairly well in conjunction with the Vickers’ designed bell-crank ‘Japanese’ type commercial suspension just some minor modifications would need to be made for it to work a bit better. The trial team also recommended the provision of air cleaners if the tank was to be used in ‘colonial’ settings.

    The thickness of the armour on the A12E1 made a sub-frame unnecessary, so the plates and castings were bolted together resulting a very smooth finish. It was noted that this form of construction needed accurate castings and many skilled-man hours to complete it. The question was asked therefore about when the production types would actually be delivered for use. The initial order for 65 ‘off the drawing board’ would likely be increased by at least 100 more, so Fowlers of Leeds, Ruston Hornsby and the LMS were all approached to take part, under the parentage of Vulcan Foundry, to contribute to production.
     
    10 May 1938. 15:00hrs. Farnborough, England.
  • 10 May 1938. 15:00hrs. Farnborough, England.

    With the Mark VI light tank in full production there had been no great desire from the War Office to look at a successor light tank design. When Vickers has shown drawings back in 1936 for what they were now calling the Vickers Mark VII light tank, it hadn’t met with any great interest, though the line of development had been given the General Staff designation of A17, and Vickers had continued developing it for the commercial market.

    With Sir John Carden’s time being completely caught up with the A9, A10, A11 and alternative A12 projects, it had fallen to Leslie Little to work on the A17. Little had designed a light tank with 14mm armour thickness, the same as the Mark VI, even though the fighting in Spain had already shown that for anything other than small reconnaissance machines this would be insufficient.

    Little had previously worked, alongside Carden and Loyd on the Bren Carrier and had taken the idea of the steering system and up-scaled it to the A17. There were four large diameter wheels, the rear acting as drive sprocket, each of which were fitted with an armoured hub to protect the wheel and inner hull. The road wheels were all pivoted on brackets and linked to the steering wheel. Movement of the steering wheel by the driver would make all eight wheels to lean and turn, the complicated geometry making the track curve and so steer the tank, rather than having to skid a track. It gave the tank the ability to drive around curves less than 94 feet, though for tighter turns, skid steering was necessary.

    Not only was the steering system revolutionary, but Little had done away with springs for the suspension, each wheel was suspended on tubular struts containing a pocket of air and a cushion of oil, which did give each wheel excellent independent springing.

    At the MEE when the A17E1 was put through it paces the problems began to mount up. Getting the tank to drive around curves wasn’t an easy thing for the driver to achieve, it took extraordinary strength to do so. Since the tracks were to curve, the pin joints were purposely made loose, in order to keep the best contact between track and wheel, however that meant that when skid steering, even at the lowest speeds, the tracks kept jumping off. Little said he would look at the design of the wheels and tracks, currently using a ball section, and change it to a square section to alleviate the problem with shedding the tracks.

    Further problems came from the Meadows horizontally opposed twelve-cylinder engine producing 180hp. There were cooling problems with this new engine which would take a lot of fixing. The other thing that the MEE noted was that Little had placed the fuel tanks in front of the driver, at the very front of the tank. Little explained that in a small tank space was at a premium, and noted that a 14mm bulkhead could be fitted between the fuel tank and the driver’s position. He also said it would be possible to organise the fuel storage compartment with a drainage system so that the fuel would drain downwards through the floor if the compartment was penetrated.

    The tank seemed to fall between two stools. It was a light tank in terms of speed and protection, but had cannon armament, rather than just machine guns. The A9 and A13, which were more regularly being called ‘cruiser’ tanks, were around 13 tons compared with the A17’s 7.5 tons. Was the A17 a ‘light cruiser’ or a ‘heavy light’ tank? It wasn’t entirely clear what the role would be, and the War Office weren’t keen on ordered a tank whose place wasn’t assured. It was noted that the 180hp engine could allow the tank to take heavier armour, though whether the steering system could cope was another matter. Once the changes were made to the A17E2 they might be in better position to judge whether or not a role could be found for it in the army.
     
    Last edited:
    20 May 1938. 11:00hrs. Newcastle-upon-Tyne. England.
  • 20 May 1938. 11:00hrs. Newcastle-upon-Tyne. England.

    Work on the design for an alternative to Vulcan Foundry’s A12 was complete, it had the company codename of ‘Valiant’. Using the A9 and A10 as his starting point, Sir John Carden had increased the length of the new design to 19’4”, the height remained 8’8½”, while the width increased to the very limit of the rail gauge at 9’. The increased width allowed Carden to get the turret ring up to the 60” that he thought would be necessary for the next gun that would replace the 2-pdr.

    As it was, the turret had enough room for a gunner, loader and commander, and there was plenty of room for ammunition storage. Just like the A9 and A10, the tank’s turret was designed for the 2-pdr gun and co-axial Vickers machine gun. There was work being done by the War Office on changing to an air-cooled machine gun to replace the Vickers. Until that appeared the water-cooled machine gun was what was offered. Carden had also designed a turret to carry the QF 3.7inch howitzer for a Close Support version.

    Like the A10, the front hull was sloped without a hull mounted machine gun. He had kept the drivers position towards the side of the tank. When the driver’s position was at the centre of the tank getting in and out when the gun was facing forward was a problem. By off-setting the driver to the side Carden had managed to provide him with an adequately sized hatch for entry and exit. If the War Office insisted on a hull machine gun, then it would be slightly simpler to implement this, if the driver’s position and all the steering controls were already off-centre.

    Carden’s ‘slow motion’ suspension system on the A9 and A10 hadn’t proven robust enough for the much heavier armour required on this A12 specification. He had designed the tank with the specified 2.75-inchs of armour (70mm) on the hull front and sides, with slightly thicker 3-inchs (78mm) on the front of the turret. With the tank now at 25 tons, Carden had opted to go back to the Horstmann designed suspension originally used on the A6E3. This used the leading and trailing bogies of the earlier Vickers’ ‘Japanese’ system, while the main central portion used a combination of coil springs and bell cranks. In 1936 this had been able to handle an 18-ton load at 30mph, so Carden was sure that it would be able to deal with the heavier load at more like the 20-25mph he expected the 400hp Ricardo diesel powered tank to produce. With lengthening the tank Carden had managed to increase the fuel capacity to give the tank a road radius of 120 miles.

    The same Meadows No 22 clash gearbox was chosen as used on the A10, though Carden had looked at the Wilson epicyclic gearbox that Vulcan Foundry were using on the A12. As a company, Vickers was more confident in Meadow’s ability to supply their gear box than the new Wilson system. Carden was aware that later marks of his A12 alternative would likely have to look at alternatives, but it was important to get things moving as swiftly as possible.

    The company executives signed off on the plans and prepared it to be presented to the War Office. A wooden mock-up was under construction and the prototype’s components were already ordered. The cost per tank, if it was to be accepted by the War Office needed to be less than Vulcan Foundry’s A12. Vickers knew that the production of the Vulcan A12 was likely to be quite slow, and so, as a sweetener, would offer to increase the workforce at their plant at Elswick build their Valiant much more quickly. If ordered ‘off the drawing board’ as the War Office had done with the A12, Vickers could promise that 100 tanks would be delivered within 18 months of being ordered, and would have the capacity to produce 30 tanks per month once full production was reached. The fact that the Valiant would be equally well armoured, but faster than Vulcan’s A12, and have the capacity to be upgraded because of the more powerful engine, meant that the company had high hopes that it would win the orders needed.
     
    10 June 1938. 10:00hrs. Belfast, Northern Ireland.
  • 10 June 1938. 10:00hrs. Belfast, Northern Ireland.

    The team from Vickers-Armstrong looked around the site that Harland & Wolff were planning on using to build the 50 A9 tanks that had been ordered from them. As with many heavy engineering companies the Belfast shipbuilders had been asked to begin getting involved in tank manufacture as part of the “augment the war potential” program. With no experience at all of building tanks the Vickers team had been brought in to help them set up production from scratch.

    The Harland and Wolff company had been moving beyond their core shipbuilding work over the past few years. In 1936 they had entered the aircraft business with Short Brothers, with a new company called Short and Harland. This had been winning orders for the Bristol Bombay bombers and had eyes on the flying boat market. They had also bought over the old Coventry Ordnance Works in Scotstoun in Glasgow, which had brought them into building naval guns and mountings for the Royal Navy. Taking on the building of tanks was another expansion of their capability.

    The Carden designed A9 was lightly armoured, and its riveted construction was well within the capacity of the Belfast workforce. That was one of the first questions the Vickers men asked, what the make up of the workforce was going to be? Obviously by expanding beyond their core business would they need to take on new workers, who would have to be trained. The Harland and Wolff team were planning on using some of their experienced shipyard men to leaven up the new workers as well as training them.

    The next question that the Vickers men had to ask was how the Belfast firm was getting on with the supply chain. Building the tank itself was only part of the task, they would also need to get the engines, gearbox and many other parts from a variety of companies. The Harland and Wolff people had been making a list of components that would need to be sourced, and which companies would need to be approached. The Vickers men, from experience, warned them that AEC, who made the engines could be slow, so it was better to order from them early and have the engines in stock before they were actually needed.

    One of the Harland and Wolff men asked how long did the Vickers men think it would take them to produce the first tank. There was a bit of sucking teeth and thoughtful looks around them at the empty space. Realistically, it would probably take twelve months before the first tank could be delivered. The question wasn’t just when the first tank could be delivered, it was also how many tanks the new production line could deliver per month. If the order remained at 50, looking at the numbers of workers that Harland and Wolff were putting onto the line, the Vickers men reckoned they would only be producing one tank per week, maybe five a month. So, if the first tank rolled out in June 1939, then production would be complete around April 1940. Having said that, the way things were in Europe and with the Italians in East Africa, the Vickers men were sure that the order for 50 would be augmented before the end of the year.
     
    1 July 1938. 10:00hrs. Newcastle-upon-Tyne. England.
  • 1 July 1938. 10:00hrs. Newcastle-upon-Tyne. England.

    The letter from the War Office was disappointing. While the design, price and delivery schedule for the ‘Valiant’ alternative to the A12 specification all met with approval, the fact that the tank used an ‘experimental’ suspension system and new type of engine, they couldn’t order the tank ‘off the drawing board’ as they had done with the Vulcan Foundry A12.

    Colonel Martel had visited Vickers and looked over the wooden mock-up of the Valiant, and at the drawings with Sir John Carden. He just didn’t believe that with the thickness of armour that the estimated 25 tons was achievable. The Horstmann suspension and the Ricardo diesel engine were likely to be a good combination, and Martel liked the fact that the turret was roomy enough to take a bigger gun. All in all, at his recommendation, the War Office would need to see a prototype put though its paces at Farnborough before they would be prepared to order it.

    What the War Office did express a desire for, was for Vickers to produce the A12 designed by Vulcan Foundry. They were particularly keen on this especially if Vickers could increase the pace of deliveries to the army. At the current rate, it would be late in 1939 before the Army started receiving A12 tanks in any numbers. If Royal Tank Corps units to be equipped with the A12 was going to be properly trained on it, it would be well into 1940 before it would be battle ready. The A11, which Carden had given the codename ‘Matilda’ to, would start arriving in army units in the February of 1939, but it would be well on in 1939 before they were fully equipped and trained. The army Tank Brigades really needed more infantry tanks sooner rather than later. Vickers had the experience and workforce to bring production the A12 forward, and so the War Office were keen to get Vickers on board.

    Sir Noel Birch, having once been the Master of Ordnance, before he joined civilian life as a director of Vickers was aware of what the War Officer were up to. The foreign orders were all very well for Vickers-Armstrong, but Vulcan Foundry’s A12 and Nuffield’s A13 were now being preferred over Vickers’ A9, A10, A11 and now the A12 Valiant. Even the A17, the new light Mark VII, didn’t look like it was going to win too many orders.

    When the order to build 100 A9s had been given, it was split evenly between Vickers and Harland and Wolff. Likewise, when the War Office ordered 100 A10s, they had decided that only 10 A10s were to be built by Vickers, while the railway carriage constructors Birmingham Railway Carriage & Wagon Company and Metropolitan-Cammell Carriage & Wagon Company got orders for 45 each. The War Office’s reason was to bring three more companies into the ‘augment the war potential’ scheme.

    This scheme had got off to a start with orders for the Vickers Mark VI light tank going to Vulcan Foundry, North British Locomotive Company; and two agricultural vehicle engineers Ruston & Hornsby and John Fowler & Co. It was Vickers that had to send off teams to show them how to do it. All these companies, and now joined by London, Midland and Scottish, were in line to get orders for the A12. It wasn’t surprising that delivery of the complicated tank was going to be slow since all the orders had gone to companies had little or no experience of building a tank.

    Meanwhile Vickers was meant to live off War Office orders for building just 120 A11s, 50 A9s and ten A10s. If the company gave into the War Office and took on the Vulcan A12, then there was almost point to having their own design team. It all felt as if with the help Vickers had given all these other companies that the tail would be wagging the dog.

    In his response to the War Office, Sir Noel Birch reaffirmed his belief that the Valiant had a much greater potential than Vulcan’s A12. Vickers would indeed create a prototype of the Valiant, which would be ready for testing later in the year. He noted that bringing all these other companies into tank production, while completely understandable in light of the program to augment the potential for war production, raised a number of questions.

    Birch noted the government’s expenditure on building new ‘shadow factories’ for aircraft production. He used the experience of Vickers-Armstrong, where the company had invested £175000 in a new tank shop and machine tools at Elswick for building the A11. While the government had reimbursed the company with 60% of that investment, with so many new firms having to create facilities to build tanks, he wondered if it wouldn’t be wise for the government to create one or more factories solely devoted to building tanks. Just as the expansion of the RAF needed an expansion of the means of production, so it would be with the army. This was particularly crucial as the heavy engineering plant and trained workers needed to build tanks would likely take longer to be ready than aircraft factories.

    A couple of new factories, with workers trained specifically for the building of tanks, with the necessary machine tools, would be a simpler solution that having some ten companies each having to create a tank shop and source the machine tools and components. He suggested that there might be one factory, under Vulcan Foundry’s parentage, to build their A12. Another, under Nuffield to build the A13. The board of directors of Vickers-Armstrong were aware that if they did receive a large order for the Valiant, in addition to their current order book, then they too would need to further expand their facilities.

    Sir Noel Birch noted that it was becoming clear that in the future it would be preferable that tanks be built using welding rather than riveting. If that came to pass then the government could augment the war potential by increasing funding for training in this skill. He also noted that there were already bottlenecks in the availability of armour plate, and so the expansion of steel plants and foundries was also a priority. It was also clear to him that the numbers of firms capable of producing guns for the tanks was going to be another bottleneck if the government wasn’t careful.

    Should Britain find itself once more at war, Birch concluded, Vickers-Armstrong's work on shipbuilding, aircraft production and weapons manufacture would be crucial to the national effort. If the War Office really wanted the army to have enough of good tanks that were needed to counter Herr Hitlers growing armoured divisions, then Vickers, the only company with the capability and designs to provide them, really needed decisions to be made soon to allow the tanks to be produced in a timely manner.
     
    1 September 1938. 14:00hrs. London, England.
  • 1 September 1938. 14:00hrs. London, England.

    Colonel Giffard Martel finished off turning his notes into a report. The General Staff specifications A14 and A16 specifications had been taken up by various companies and Martel had travelling around the country inspecting progress on these and the other tanks being designed and produced. In each case the specifications for A14 and A16 were for what might be described as a ‘battlecruiser’ tank. The origin of these was Martel’s visit to Russia where the T28 had given him the idea of something between the fast Christie style BT2 and the heavy infantry tanks. Nuffield’s A13 was progressing looking much like the BT2, while Vulcan Foundry’s A12 would be a slow but heavily armoured infantry tank. The Soviet T28 tank's armour was between 20-30mm, but it weighed over 25 tons; but since it had a 500hp engine it moved at a reasonable 20mph.

    In 1936 the A6, Vickers 18 tonner, had been similar to what the Soviets had, a Medium tank, but was deemed too expensive. So, in 1937 London, Midland & Scottish had been approached to take on a specification A15 that would be an updated but cheaper A6. Like the earlier machine it would be well armed, with two machine gun sub-turrets in addition to the main turret. This would be designed to carry both a 2-pdr and a close support howitzer together. In addition to having two main guns, it would also have both a co-axial machine gun and another machine gun positioned to protect against air attack. Unsurprisingly the problem with the specification was that not matter however long and high the design went to fit in all that was required, it couldn’t be kept within the width of the railway loading gauge. That had led to a discussion within the War Office whether to give permission to build the A15 to suit the continental loading gauge which would give another ten inches width to play with. The idea of British tanks being used on the continent however couldn’t be imagined, so the idea, along with the specification had been shelved back in December 1937.

    The notion of a fast but heavily armoured cruiser as a replacement for the Mediums hadn’t gone away, which is why the A10 specification had been issued to Vickers. The War Office however still wanted to explore the idea so LMS and Vulcan had been approached with the A14 specification. This specification, not unlike the Vickers A10, was for a tank with 30mm of armour, but like the original A6 and A9, it would have a crew of six, three in the turret with a 2-pdr and two sub-turrets with machine guns. LMS picked up the idea, using the A6E3 as a basis, with Horstmann suspension, a Thornycroft RY12 marine diesel, and a new form of Wilson steering that offered a choice of seven speeds for each track, on a preselector basis. This made it heavy and complicated, but as a steering system it was considered an improvement over skid steering because it did not waste power.

    LMS had no experience of designing or building tanks, it was first and foremost in the railway engine and rolling stock business. Looking at the design and their progress so far, Martel estimated that the prototype wouldn’t be ready at least until mid-1939, and he was of the firm conviction that it would be much heavier than expected or desired. The process of learning to build a tank from scratch was slowing the company down. What he did note was that what LMS was proposing was capable of expansion to meet future GS requirements, but he reaffirmed his suspicion that the company would struggle to actually produce a tank that would be suitable for entry into service.

    The second company working on the idea of a heavy cruiser was Nuffield. When they had been approached with the requirement, they offered a heavier version of the A13. This had been given the GS specification A16. Again, it was designed with a crew of six, the same turret as the A14, in fact this would be made by LMS, along with the two machine gun sub-turrets. It would also have 30mm armour and a stronger version of the Christie suspension. It would use the same Liberty engine as the A13 and initially the same steering and transmission. Martel noted that they were also looking at a more sophisticated system, based on a controlled differential linked to a Maybach constant mesh gearbox designed by Thompson and Taylor of Brooklands. In his report Martel noted that this design also had the potential of being upgraded in the future, though he questioned whether the Liberty engine would be capable of increased power. Martel noted that the company, based on Morris Motors, was in a better position than LMS to producing tanks. Their work on the A13 was progressing well, but whether they could produce both designs in a timely manner was debatable.

    Which brought him Vickers. Progress on the A9, and A10 cruisers as well as the A11 infantry tank were all noted as good. While the A14 and A16 kept the two forward machine gun turrets in addition to the main turret, Martel noted that the Vickers A9 had deleted these, which Martel regretted in his report. It had led to a slight increase in armour thickness while not impacting on its speed. Compared with the Christie suspension on the Nuffield A13, the speed of the A9 wasn’t that impressive. The same could be said of the A10, which with the 30mm armour specification was, despite the use of welding to lighten it, just a bit too heavy for the AEC bus engine. The alternative and experimental A10E2, with the Rolls Royce Eagle aero-engine, had been much more impressive. The greater power it provided made sense when compared to the Soviet T28’s 500hp engine that gave a heavier tank greater speed. The A10, like the A9, Martel noted, suffered from the suspension limiting the speed, even with the Eagle engine. Martel noted that at about 16 tons fully laden, the A10 was about ten tons lighter than the T28, but not that much faster cross-country.

    The A11, for which the Vickers codename was Matilda, wasn’t far from the first production models being delivered. Martel had previously noted the limitations of the A11 which he judged was underpowered. The use of the Vickers own 40mm pompom gun meant that the turret looked top-heavy to Martel, but he judged it a reasonable tank for the Army Tank Brigades, even if in his own mind this was only on the principle that something was better than nothing. Martel noted that orders for 100 each of both the A9 and A10 had been made, and delivery would take a year at least.

    Martel had also looked over the A17, Vickers Mark VII light tank. When it had been shown, with Little’s warp steering, someone in the War Office had wondered whether it could be expanded, and so specification A18 had been issued. This basically was to use Little’s suspension system in place of the Christie suspension in a tank like the A13. It was obvious to Martel that there was no enthusiasm in the Vickers team for the work on this specification. The warp suspension worked very well in the much smaller bren carriers, and just about well enough in the Mark VII light tank; but putting it under something in the 14 ton range was likely to asking too much of it. Once more the two sub-turrets for machine guns had been part of the specification and Martel had had a hard time from Carden about the War Office’s fascination with this requirement.

    The last matter in Martel’s report was the alternative A12 design, called Valiant by Vickers. He had had a number of conversations with Sir John Carden and knew and understood what it was he was trying to do. The Vulcan Foundry’s A12 was a very good tank, but Martel could see Carden’s point that it would be slow to build, and didn’t have any potential to be upgraded. The Valiant was already going to be faster that Vulcan’s product, but with the powerful diesel engine and bigger turret ring meant that it had room for improvement. Should the Valiant prototype pass the MEE tests, it may well be available from mid-1940. With all that was going on at the border between Germany and Czechoslovakia, Martel couldn’t help but note that mid-1940 might be later than the tank would actually be needed.
     
    1 October 1938. 10:00hrs. Newcastle-Upon-Tyne. England.
  • 1 October 1938. 10:00hrs. Newcastle-Upon-Tyne. England.

    Like most of the men turning up for work that day, Sir John Carden had read the newspaper reports of Prime Minister Neville Chamberlain’s “Peace in our time” speech. As he entered Sir Noel Birch’s office and took a cup of tea that was the only topic for conversation.

    Birch’s contacts in the army had been on high alert. There had been quite a lot of watching of the German army’s preparations for the possible invasion of Czechoslovakia. The War Office was buzzing with rumours and counter-rumours about what would have happened between the German troops and the Czechs if it had come to war. Knowing how the German Condor Legion were doing in Spain, there weren’t too many who gave the Czechs much hope for success.

    Reading between the lines of all that had been going on, Birch was of the firm opinion that re-armament was now very firmly on the agenda for Britain. It wouldn’t be just the Royal Navy and Royal Air Force either, the chances were that the British army would soon be thinking seriously about a British Expeditionary Force. Obviously, Hitler wasn’t going to be satisfied with just the Sudetenland, and looking at the state of the British army, especially its tank forces, Birch hoped that Chamberlain had bought the country enough time to get its act together. Carden noted that especially now that the Germans would likely benefit from Czechoslovakian industry, including tank manufacturers, the need for rearmament was ever more pressing.

    The first 60 A11s which had been ordered in April 1937 were under construction and progressing well. Deliveries would begin in the new year and be completed before the summer of 1939. The second and third batches, for another 120 tanks, which had been ordered in April and September 1938, would be for the A11 mark II. The army had been persuaded to allow Vickers to replace the Meadows engine (used in the light Mark VIB tank) in the A11 mark I with the AEC bus engine, producing 135hp, as used in the A9 and A10. This would give the 12 ton tank a bit more power and therefore speed, taking it up to about 10-12mph. The first 60 A11 Mark IIs would be in the hands of the army by Autumn 1939, the other sixty being delivered in the winter of 1939/1940. Knowing the problems with Vulcan Foundry’s A12, Birch was confident that the company would receive orders for more A11s before the end of the year.

    The fact that the most recent order for another 70 Mark VIbs had just been given to Vulcan Foundry was interesting. There had been a downturn during 1937 and Vulcan had shed workers that year. The War Office was obviously concerned about the A12 program that giving such a large order of light tanks to Vulcan Foundry was an incentive to increase the workforce so that when the A12 went into full production they would have the men to build it. So even although there was a recession during 1938, Vulcan, like Vickers, had been expanding the workforce.

    What concerned Carden was how the company were going to get the Valiant into full scale production. If the last order for the A11 was only being fulfilled in early 1940, then realistically that would be when the Valiant would be able to be produced. Birch was confident, from his conversations with Martel at the War Office, that allowing for the prototype to successfully complete its trials, then a substantial order, over 200 Valiants, would follow. If that came before the end of 1938, then beginning to produce the Valiant in early 1940 would be about right. That would mean the first fully equipped and trained units would be ready around the late summer of 1940.

    An alternative suggestion from Carden was for the company to do in Chertsey what it had done in Elswick: expand the facilities and create a new tank shop. Creating a complete tank factory would take about a year, but it would mean that orders for the Valiant would more likely stay within Vickers itself rather than going, as with the A9 and A10, to companies like Harland & Wolff, Birmingham Railway Carriage & Wagon Company and Metropolitan-Cammell Carriage & Wagon Company. If war was coming, then the dribs and drabs of orders for tanks from the War Office would become a flood. If Vickers had the production facilities to put its designs into fast production, then the company, and the country would prosper. Hopefully Neville Chamberlain had won the country enough time to rearm, because neither Birch nor Carden really believed that there would be peace in their time.
     
    1 November 1938. 10:00hrs. Birmingham, England.
  • 1 November 1938. 10:00hrs. Birmingham, England.

    The Birmingham Small Arms factory had acquired the rights to build the Czechoslovakian ZB 53 machine gun at the behest of the War Office. With the situation in Czechoslovakia the company were worried that the German takeover would complicate matters.

    The company had therefore sent one of its engineers to the Zbrodovka Works in Brno to get the all the paperwork and blueprints that the agreement had promised. It was all a bit cloak and dagger, but he successfully returned to Birmingham with all the company needed.

    The problem now was getting everything translated and transferred from the metric to imperial measurements. The original plan had been to adapt the gun to accept the rimmed .303 round, but the Royal Tank Corps agreed to accept the belt-fed version provided that it remained in its original form with the 7.92mm round.

    A team was convened at Small Heath and work began to try to put in place the work that would be needed to prepare to put the gun into production. Once the blueprints had been translated the company would need to work out what machine tools would be needed, the training of workers and the sub-assemblies and raw materials that would need to be ordered. The army was keen to get the guns as soon a possible, but the managers reckoned it would be at least six months before the first guns would be available. Realistically to get to full production, about 200 per month, might take another year, depending on how many problems had to be resolved.
     
    12 December 1938. 16:00hrs. Farnborough, England.
  • 12 December 1938. 16:00hrs. Farnborough, England.

    The Valiant prototype had been delivered to the MEE and had the first few days of its trials already. Sir John Carden had, unusually, spent the day along with the team. The prototype had been somewhat rushed to get it delivered as quickly as possible. The Ricardo Consulting Engineers had been taken a Napier Lion engine and made it into a diesel. As with most things, the first one had taken longer than expected, and Carden had been worried that it would let the prototype down. A team from Napier and Ricardo had also come along to keep an eye on their creation. An alternative was under wraps in case it had to be pulled out and replaced. So far, it was running well, providing the expected 400hp, but the tests weren’t finished yet.

    The suspension system was well known and tested on the old A6E3. Sydney Horstman and John Carden had looked at it as it was being put onto the prototype and made a few minor changes to strengthen it and make it as effective as possible. They had a conversation about looking at improving it further as the weight of tanks was inevitably going to increase, so the suspension would need to improve too. In the meantime, as suspected, the suspension was more than sufficient for the Valiant’s 25 tons. The suspension combined with the engine gave a maximum road speed of 23mph in the speed trials.

    The cross-country performance had also been successful, fording a depth of 3 feet, a clearing a vertical obstacle of 2’9”, crossing a trench 7’6” wide. The range on the tank of diesel fuel was 120 miles. All in all, the tank performed as promised, if not a bit better that those from the War Office hoped. In a straight test between Vulcan’s A12 and Vickers’ Valiant, the Valiant was superior in all areas to the A12, except the radius of action. At £1700 it was a little cheaper than its competitor, and much more importantly, Vickers would be in a position to build it much more quickly.

    To say that the men from the Royal Tank Corps were keen was an understatement. In terms of armour and armament it was an infantry tank, but its speed wasn’t that far off what the Christie suspension ‘cruiser’ tank was offering. The Valiant would be able to fill the roles in both the army tank brigades supporting the infantry and in the armoured divisions. The fact that Carden had designed the Valiant with room to grow was another factor in its favour, it was something that the Vulcan A12 didn’t offer. The War Office had already ordered 220 A12s and 180 A10s for the army tank brigades. There was a hope that there would eventually be five of these brigades, which would need 150 tanks for each Brigade, a total of 750 infantry tanks. If 300 Valiants were ordered that would complete the requisite numbers. If only the Treasury could be persuaded, Vickers-Armstrong could be able to begin deliveries in early 1940.
    Claymore'sValiant3.png

     
    10 January 1939. 10:00hrs. Newcastle-Upon-Tyne, England.
  • 10 January 1939. 10:00hrs. Newcastle-Upon-Tyne, England.

    Sir Noel Birch, before he had retired from the army and moved into civilian life in Vickers-Armstrong, had given his name to a self-propelled gun. Birch, with Vickers help, had tried various attempts to mate an artillery piece and the hull of a tracked vehicle. The conservativism of the army had ultimately put paid to the experiments, but Birch still thought there would be a place for the Royal Horse Artillery equipped with tracked vehicles that could keep up with tanks. With the various designs now being worked on by Vickers-Armstrong, he had given his blessing to Sir John Carden to look again at a self-propelled gun.

    Carden had already thought of this and had some sketches and drawings that he had been working on. The original Birch gun had been an 18-pdr*, most of these were being adapted to the new 25-pdr that was standard for the artillery regiments. Carden had noted from the debates around the Birch gun back in the 1920’s that, in his opinion, part of its failure was trying to do too much. Instead of mounting it in such a way that it could be rotated 360°, as well as be elevated to be used in an anti-aircraft role, his own design was for something much simpler. Using the Valiant hull as his basis, he had been able to position the 25-pdr gun inside a raised armoured casement. By its nature it had to open-topped, but since it wasn’t envisaged to be in direct contact with the enemy, this seemed reasonable. It would provide a greater mobility than guns towed by tractors (either wheeled or tracked) and at least some protection for their crews. Unlike the old Medium Mark II hull, the Valiant’s would be far more capable of dealing with the recoil of the gun. They talked over what they might call it, and decided eventually on ‘Vampire', it would have a good bite.

    Birch had approved Carden’s plan and the two men had approached Giffard Martel for his blessing to build a prototype Vampire for the Royal Artillery. They didn’t imagine that it would win too many orders currently, but Birch was of the firm belief that the original idea that had led them to experiment in the 1920’s, the experience of the Great War, would likely have to be relearned. He still had friends in the army, and had spent time on a shooting meet over the Christmas holiday with General Alan Brooke, the commander of 1st Armoured Division. As an artillery man, when Birch had talked about self-propelled guns able to keep up with his tanks, Brooke had expressed some enthusiasm for the idea. That had led to a further discussion about what he was learning from commanding the Armoured Division.

    The ideas that had been around from the experimental Mechanised Force, which Noel Birch had been part of, showed up that all the supporting arms needed to be in vehicles that didn’t have to stick to the roads. Having a Royal Horse Artillery regiment on self-propelled guns would be great, but the combined Light Anti-Aircraft and Anti-tank regiment would also need more tracked vehicles. The two motorised infantry battalions and the Royal Engineers also needed to be able to go wherever the tanks could go. The Engineers needed bridging equipment and be able to deal with minefields. Brooke also thought that the RAOC and RASC, bringing forward all the supplies and ammunition, as well as fixing whatever was broken, needed to be integrated into his Division’s command chain. But his largest gripe was that all he had so far were light Mark VI tanks and a few older Mediums. It would be lovely to have a fully mechanised Division to back up his tank regiments, but without tanks, everything else was ultimately pointless. Brooke had been privy to the Valiant's testing at Farnborough and he was most keen on getting a Division's worth as soon as possible.

    When Birch shared this conversation with Carden, they began thinking about what would be adaptable for the various roles to support an Armoured Division. Not everything needed the heavy hull of the Valiant. The A9 hull, with its relatively thin armour, and reasonable speed, was big enough to use as the basis for something that could take the proposed Bofors 40mm anti-aircraft gun for the light AA regiments. Surrounding the gun with a bullet-proof shield might give it a very high profile, but since it wasn’t expected to close with the enemy, just protect the gunners from bomb fragments and strafing, that would matter less. ‘Vanguard’ was the name they gave to the self-propelled anti-aircraft gun (SPAAG) idea, guarding against aerial attack. They discussed whether the Valiant hull might be capable to carrying the new 3.7-inch anti-aircraft gun for the Heavy Anti-Aircraft regiments, but Carden thought the gun was probably too heavy.

    Carden did note that the older 3-inch gun would be much more feasible, and like the old Birch gun Mark II, it could probably be mounted for both anti-air and direct artillery support. The two men also wondered about using a lighter anti-aircraft gun on the mounting. Something like being used as bombers’ defensive turrets with two or four machine guns would easy enough to mount on a tracked hull, even the Mark VI light tank*. Birch did not think that just rifle calibre machine guns would be entirely suitable for that role, that perhaps the 20mm Swiss Oerlikon that was being looked at might be better. Then he mentioned Vickers own 2-pdr pompom in the A11 turret. The Mark XVI mounting that the Royal Navy used could probably be adapted for use in a tank hull. Carden certainly knew the pompom would be easier to get his hands on to try it out, though the A9 hull would be needed for that. What advantage this would have over the Bofors 40mm gun wasn’t entirely clear to Carden, but perhaps it would be a stop-gap until enough of the Swedish weapons were available.

    As for the 2-pdr anti-tank gun in a protected casement, like the idea of the Vampire self-propelled gun, Carden didn’t believe that the War Office would be interested in such exotic ideas. There already had been experiments the previous year using the Vickers carrier to mount a 2-pdr*, to give it the kind of mobility that couldn’t be achieved with the towed version. However, the War Office had been quite dismissive of the prototype. Carden didn’t mind trying something different, perhaps using the A17 hull as the basis. It would be simple enough to build up the shield to give all around protection to the crew even against an anti-tank round, though that might need the A9 hull. Without a turret, the vehicle would have a low profile, and still be big enough to mount whatever gun followed on from the 2-pdr. They decided to name this project 'Vixen', it might appear small but combatative.

    Something of what General Brooke and Noel Birch had talked about gave Carden an idea for the motorised infantry. The French and Germans were experimenting with using half-tracks for carrying infantry. Why not go the whole way with an ‘armoured personnel carrier’. This had been the idea behind the Cavalry Carrier*, designed to carry six soldiers into battle, but it wasn’t gaining much traction with the Cavalry regiments. The idea of carrying troops into battle and then fighting dismounted wasn’t quite the way they were thinking of themselves in the mechanised era. Whereas the infantry, supporting the tanks in an Armoured Division, might just, finding themselves more mobile and better protected, more able to carry out their support role. The Cavalry carrier was too small for carrying a section of soldiers. But the A17 hull, basically an expanded carrier, would be big enough to carry eight or even ten troops. Birch wondered if mounting the engine at the front, like on the Mark VI light tanks, wouldn’t give a better sized and protected compartment to carry the infantry, allowing them to be able to dismount from the rear of the vehicle. Carden didn’t think the bigger Meadows engine in the A17 would allow for that, but he would be happy to give it some thought.

    The other vehicles that the Armoured Division needed: bridgelayers, minesweepers, bulldozers, recovery vehicles were all within the bounds of possibility on either the Valiant or A9 hull, in fact, even the A11 could be adapted if necessary. The Royal Engineers would need to be consulted on what exactly they would be looking for, but Vickers had a solid basis in its various tanks to offer them the capability of having the right vehicles for their roles. They debated whether producing a lengthened version of the Mark VI light tank chassis could give the RASC and RAOC a tracked and protected lorry for carrying fuel, ammunition and supplies forward. Though, they had to admit, in reality the tracked carrier was already suitable for much of that work, so perhaps making a bigger version capable of carrying more weight might be the better solution.

    Sir John Carden had plenty of notes from his meeting to work on. Calling together the design team, all those not currently involved in essential work, were given tasks to see whether Vickers could produce vehicles that the army didn’t even know it needed yet.
    *
    birch-7.jpg

    *

    320px-Bren_Anti_tank.jpg

    *
    MarkVISPAAG.jpg

    *
    3cavcarrierfig3.jpg
     
    Last edited:
    20 February 1939. Lulworth Camp, Dorset, England.
  • 20 February 1939. Lulworth Camp, Dorset, England.

    Armoured Fighting Vehicle School of Gunnery played host to the first two completed A9 cruiser tanks (T3492 and T3493) to enter service. Manufactured in the Elswick plant by Vickers-Armstrong, the newest tanks in the army had come to be put through their paces as gun platforms. Almost everybody from the various Royal Tank Corps units had found excuses to make their way to Dorset to have a look over the new tank.

    Having been used to nursing the obsolete Medium Mark IIs through exercises, the fact that brand new tanks were coming along was a relief. All things considered the A9 was clearly a new generation of tank compared to the Mediums. The AEC Type A179 6-Cylinder Petrol, providing 150 hp, moved the tank along at a healthy 25mph on the road, while the ‘slow motion’ suspension kept the tank as a reasonably good gun platform at 15mph. Compared to the Medium Mark II, which had a 90hp engine, whose top speed was once 18mph on the road and 10mph off it, the new tank felt quick. It had been quite a while since the Mediums had managed to get up to those speeds since their engines and suspension were worn out.

    For the gunners the 2-pdr gun provided them with something that the old QFSA 3-pdr didn’t, the ability to actually penetrate armour plate targets at a thousand yards. The old gun fired a round at 1,840 ft/s, this had now been replaced with one that fired at 2,600 ft/s and the gunners were going to need a lot of practice time to get used to the gun and its new sights. Hitting a target on the move, when your tank is moving faster than you are used to, wasn’t going to be easy. The instructors were familiarising themselves with the tanks to the point where they could properly instruct the rank and file of the RTC and Cavalry regiments that would need to be trained on the gun.

    There were all sorts of other innovations and improvements over the old Mediums in the A9. The hydraulic power turret traverse made keeping the gun on target while moving a good deal easier, though the instructors soon discovered that for final fine tuning they preferred to use the manual controls. The armour protection for the crew had increased from a third of an inch to three-quarters of an inch. Having only a co-axial and hull mounted machine gun provided the tank with less fire power than the Medium Mark II had. The three machine guns in that tank had provided a wider field of fire, but the instructors at Lulworth were happier that there were fewer jobs for the crew to carry out. The idea of using the hull gunner as the wireless operator had initially been resisted, but once again the intercom borrowed from the Wellington bomber had eased their concerns. The tank commander was in a much better position to command the tank, while the positioning of the radio in the hull gave more space to carry ammunition for the guns.

    The balancing of the gun, without the radio in the rear of the turret, had been achieved by Vickers in a satisfactory way, and the Royal Tank Corps instructors were overall very happy with the A9. A few of the men based at Lulworth had taken part in the trials of the Medium Mark III (A6 and A7)prototypes, and could see that Sir John Carden’s design of the A9 had given them a tank that fulfilled the potential they had seen in those prototypes. Once the first Close Support versions started arriving from Harland and Wolff, the RTC would be in a position to properly equip itself. The delivery of the first tanks from Belfast wasn’t expected until June. There was a lack of armoured plate and so some had had to be ordered from Böhler in what had been Austria. It was somewhat embarrassing that tanks that were designed to counter the rising threat of fascism were being built with steel from the Greater German Reich!
     
    28 February 1939. Lulworth Camp, Dorset, England.
  • 28 February 1939. Lulworth Camp, Dorset, England.

    It seemed to the Royal Tank Corps that tanks were like buses, you waited for ages for one to come along and then three arrived at the same time. Having had the first couple of A9s to get used to for a week, the first of Nuffield Mechanisation and Aero’s production of A13s had been delivered. If the A9 felt fast after the experience of the Medium Mark II, the A13 was positively speedy. The Liberty engine had had to be governed to keep the top speed on the road down to 30mph. What had really rattled the teeth of the instructors at both Lulworth and Bovington was doing up to 24mph cross country. The turret on the A13 differed from the A9 only in having the wireless set in the rear. Otherwise the gunner and loader positions were much the same, though there were some differences in the stowage of ammunition. For the gunnery instructors this was a blessing because they could use either turret for training. Delivery of the A9 and A13 would be relatively slow, so having a similar arrangement on both tanks simplified the job of the instructors. A number of training stands for the 2-pdr gun had been delivered so the initial training could be carried out before letting the new gunners loose in a tank turret.

    What the speed of the A13 gave the crew was a sense of protection. Although the armour was only half an inch thick, an enemy would be hard pressed to hit a target moving at more than 20mph. For the gunnery instructors however, hitting a stationary target from a vehicle moving at more than 20mph would take some doing. Even worse would be trying to hit another tank that was also moving from a fast-moving position. The idea of stopping to shoot was anathema to the instructors, though they were beginning to see the value in at least slowing down. From that point of view the A9 was a slightly better gunnery platform, its slower speed over the cross-country parts of the range gave it an advantage in hitting another target. On the other hand, the A13’s top speed made it a firm favourite of tank commanders.

    The third production tank to arrive was the new infantry tank, A11, from Vickers whose code name for it, ‘Matilda’, had been adopted by the RTC men. It was nice to call a tank by a name rather than a designation. Compared to the A13, the Matilda was a tortoise compared to a hare. With a crew of only three it was a good deal smaller than either the A9 or A13 and felt cramped in comparison. Vickers had somehow managed to shoehorn into the turret both a 2-pdr pompom gun and a .303 machine gun. Once the Besa air-cooled machine gun was available, this would make life a little easier as it would take up less room.

    The pompom gun was designed primarily for the Royal Navy as an anti-aircraft weapon, its muzzle velocity was considerably less than the 2-pdr anti-tank gun. The gunnery instructors found the magazine for the semi-automatic gun slightly difficult to load in the cramped confines of the turret. In trials the advantage of the HE round against soft targets was clear, and, since it also had an AP round, even against armoured plate it fared quite well.

    This led to a lively debate in the Sergeant Mess later in the evening about the merits of a gun that could take on both soft and hard targets. An HE shell for the 2-pdr tank gun was available in small numbers, but the explosive charge was little better than a hand grenade. Therefore, it needed to be fired every bit as accurately as an armour piercing round. The pompom gun’s HE round’s explosive charge wasn’t that much more powerful, but the faster rate of fire meant that it could put a few HE rounds in and around a target, destroying it effectively. The debate got a bit heated when considering what would happen if the infantry tank had to take on well protected bunkers. There were those who would prefer having a tank equipped with something more like a howitzer to be able to take on such a target. Others argued that that was the role of the artillery and that tanks shouldn’t be used as a solution to something that wasn’t their problem.

    The Meadows 88hp engine, the same one used in the Mark VI light tanks, just about pushed the much heavier A11 along a road with a top speed of 11mph, though downhill, with a following wind, it might just make 13mph. Cross country, 8mph was about as much as it could muster. With 2.3 inches of armour the crew felt very protected, even the 2-pdr gun would have problems penetrating this thickness from anything more than point-blank range. Once again, this led to a debate in the Sergeant’s Mess about what kind of gun would be needed as an enemy began producing tanks with the same kind of armour thickness.

    Since the Matilda would be going to the Army Tank Brigades rather than the Armoured Brigades, its slower speed compared to the A13, and even the A9, wasn’t an issue. Its pompom gun was considered adequate, and although it was different from the 2-pdr, instructing gunners on it wouldn’t be too difficult. Once the bigger A12, with the standard 2-pdr, started arriving from Vulcan Foundry the Tank Brigades would be better off, but as an interim tank, the Matilda was very welcome.

    AH Matilda A11 Mk II.png

    IWM-KID-358-A13.jpg
     
    6 March 1939. 16:00hrs. Farnborough, England.
  • 6 March 1939. 16:00hrs. Farnborough, England.

    Sir Campbell Clarke, Deputy Superintendant of Design at Woolwich Arsenal, once remarked that ‘if you don’t keep a firm hand on weapon policy on tactical grounds, the General Staff goes a-whoring after foreign weapons every few months, but it is useless to talk technicalities with them.’ So it was that the Czech TNH/P tank had arrived in England, thanks to Lord Nuffield and Morris Commercial. The tests on the 8-ton tank left the MEE pretty impressed. The design was considered fine, the tracks were particularly impressive, something that was passed on to various British companies. There were a number of issues that were noted. One of these was how the bow gunner couldn’t sit back comfortably as the wireless was at his left shoulder. The one major problem with the design that the British couldn’t live with was the gun mounting. It had to be locked before the main armament, a 37mm gun, could be fired. Along with the rough suspension it meant that the gun could only be fired if the tank came to a stop. This was unacceptable to the British way of thinking, and so the Czech tank was rejected as a possible addition to the Royal Tank Corps.

    As the Germans were in the process of taking over Czechoslovakia it was noted that this type of tank might be taken up by the Wehrmacht to supplement their panzer forces. There wasn’t a great deal of information about the German tanks, so the Royal Tank Corps studied the Czech design quite intensely to see what its strengths and weaknesses were from the point of view of meeting it on the battlefield. As a light tank, armed with an anti-tank gun it was a direct threat to all the British types except the infantry tanks. The A9 and A13 cruisers were no better protected than the Mark VI light tank. The 37mm gun was judged not as effective as the British 2-pdr, but it would be more than adequate against half an inch of armour plate. The question of increasing the armour on the cruiser type tanks had already been discussed and the A10’s slightly more than an inch of armour would be needed as a minimum against the 37mm gun.

    When Nuffield were approached with the question about increasing the armour on the A13 they responded positively, the engine and suspension would have no problem with the extra weight. So, they designated the A13 Mark II as having 1.1 inch armour as standard. Once that had been done there was no need to proceed any further with work on the A16 specification for a heavier tank based on the Christie suspension.

    The various War Office designations (A9, A10 and so on) were giving way to a more generic Cruiser/Infantry tank nomenclature. So, the Vickers designed A9 was now called the Cruiser Mark I and the A10 was Cruiser Mark II. Nuffield’s A13 was Cruiser Mark III, so the A13 Mark II would be called the Cruiser Mark IV. The Infantry tanks, A11 and A12 were now Infantry tank Mark I and II respectively. The Valiant would be the Infantry tank Mark III when it appeared.
    (Image from "The Great Tank Scandal" by David Fletcher HMSO, London, 1989)
    Czech1.jpg
     
    5 April 1939. Bovington, Dorset, England.
  • 5 April 1939. Bovington, Dorset, England.

    Yesterday’s Army Orders were still being digested, along with many a hang-over. King George VI had approved the formation of a Royal Armoured Corps. This brought together eighteen Cavalry regiments, eight battalions of the Royal Tank Corps, and its twelve territorial battalions, along with twenty-one yeomanry regiments.

    At the headquarters of what had once been the Royal Tank Corps, it felt like a bitter pill to be reduced to the Royal Tank Regiment. The creation of Tank Corps from the Heavy Branch of the Machine Gun Corps had been crowned by the Royal Warrant in 1923. The Royal Tank Corps had had to fight its corner during the lean years of the post-war period. In its favour, the tank had proven an effective weapon, not only of war but also of popular imagination. Somehow it exemplified the final breaking of the stalemate of trench warfare that had eviscerated a generation of young men.

    It seemed that the mechanisation of the Cavalry which had begun in 1928 had proven the argument that the RTC embodied: the future of warfare was mechanical. The officers and men of the RTC had seconded to all the ‘donkey whallopers’ as they came to terms with machines rather than horse-flesh. Generally, the process had been slow and steady, the lack of suitable vehicles for training always being the limiting factor. The creation of the Royal Armoured Corps (RAC) was logical from the army’s point of view, but the Royal Tanks had been a Corps, and were now simply a Regiment, somehow it felt like it was a demotion.

    The 59 RAC regiments had the potential to be an extraordinarily powerful force. But it fell so far short of its paper strength, that it was almost laughable. Nobody in Bovington was laughing, especially those feeling the worse for wear. Some Cruiser and Infantry tanks were beginning to arrive, only enough for some training at this point. Training the mechanics, training the drivers, training the loaders and gunners, training the tank commanders would all take time. That was before the regiments would be able to train with the tanks, learning how to make the best use of them on a modern battlefield. Mr Chamberlain had assured the country of ‘peace in our time’, but nobody in the army had any real doubts about the looming prospect of war. The Royal Tank Regiment would be at the heart of the Royal Armoured Corps, how they could influence all the Cavalry regiments, regular and yeomanry, to learn the new way of war would be critical. That at least was something they could work on, while waiting for the tanks.
     
    12 April 1939. London, England.
  • 12 April 1939. London, England.

    Sir John Carden had arrived back from Belgium the previous evening. He travelled far more by train these days, it was slower, but somehow the experience of nearly crashing back in December 1935 had put him off flying for good.

    He had arranged this meeting at Woolwich Arsenal to review the progress being made to the successor to the 2-pdr anti-tank gun. The choice of a six pounder (57mm) gun was due in no small part to this being a familiar gun in naval service that already had the tooling available. As the gun was likely to be required for future Vickers-Armstrong tanks, Carden was keen to see what progress was being made. There was only a small team working on the project, the whole of the Arsenal was inundated with lots of requests for new equipment for the rapidly rearming army, navy and air force.

    While his primary interest was in the size and weight of the gun to be mounted in a turret, Carden was also curious about the new gun’s capability. The design team were confident of the gun, firing at 2650fps being able to penetrate 70mm of armour at something over 500 yards. That was the specification they were working to. When Carden noted that the Vulcan A12’s thickest armour was 78mm, the team said that they knew that. Knowing that his own design of the Valiant would include even thicker armour at some point he wondered what solutions there would be for 80, 90 and 100mm. The design team did some calculations on the back of an envelope and messed about with a slide rule. They thought that kind of armour would need a gun somewhere around the weight of shell of the 25-pdr and muzzle velocity of the 3.7-inch AA gun.

    When Carden had been in Belgium looking over what they were doing with the various Vickers products they had equipped cavalry units with, he had also taken a side trip to France. His contacts had allowed him to have a look over the work being done by Renault, SOMUA and Hotchkiss. The British had increased the requirement for the basic level of armour to 30mm, the French were already thinking about the 40-50mm range. Having seen the demonstrations of the 37mm gun on the Czech tank that had been in Farnborough for examination, Carden could only imagine that teams like this one in Woolwich were beavering away trying to sort out something with a bigger punch.

    The other thing he noted from the B1-bis was that it carried the 75mm gun in the hull as well as the 47mm anti-tank gun in the turret. He didn’t like the design, it seemed to him too complex for the crew to handle. But it was a solution to a problem: one gun to take on other tanks, another gun to support the infantry against fixed positions or anti-tank guns. So, he asked whether there were plans for an HE round for the 6-pdr? The design of ammunition wasn’t this particular team’s forte, but as they understood it, such a shell was envisioned. Whether it would be any more effective than the 2-pdr’s anaemic HE capability, Carden suspected it wouldn’t be.

    His own inclination for the follow up version of the Valiant was to skip the 6-pdr and just go for something bigger. He kept coming back to Martel’s description of the Soviet T-28 with the 76.2mm gun. The 3-inch gun, like the six-pounder, was a familiar calibre for both naval and anti-aircraft use. It too had the tooling already available. It might not have the size of shell of the 25-pdr or the muzzle velocity of the 3.7-inch AA gun. What it did have was far more potential, in his opinion, than the 6-pdr, for both the anti-tank and infantry support roles. Using the Close Support requirement, currently the 3.7-inch howitzer as a cover, he had already asked the gun design team at Vickers to look at adapting a 3-inch 20 cwt AA gun to able to be fitted in an enclosed turret. Looking at what was going on at Woolwich, Carden was confident that the progress in Newcastle-upon-Tyne on that gun was probably as advanced as on the 6-pdr here in Woolwich Arsenal.

    Getting the gun right was one thing, but if the turret was going to have to be big enough for such a large gun, he would have to look again at the turret ring size. The 60-inchs he had put into the Valiant wasn’t bad, but realistically it would need to be bigger again.
     
    1 May 1939. Wolverhampton. England.
  • 1 May 1939. Wolverhampton. England.

    The 2nd Dragoon Guards, the Queen’s Bays, had been assigned the first few of the new Light Tank (Wheeled), designed and built by Guy Motors of Wolverhampton. This was basically a four wheeled drive armoured car, but because its turret was fully enclosed, with the same armament as the Vickers Mark VI light tanks, it had been renamed as a Wheeled Tank.

    With a body made of 14 mm of armour, its centralised driving compartment was in front of the main superstructure which mounted a square turret with the Vickers .5-inch and .303 machine guns. It was the first fully welded vehicle brought into service by the British army. The welding made it better protected against small arms and more waterproof, thus being able to ford water bodies easier. Welding even made the vehicle slightly lighter. In addition, it made the vehicle a lot cheaper and quicker to build. The welding technique developed by Guy Motors was then given to the War Office, for free. This had brought Sir John Carden and a team from Vickers-Armstrong to have a look at what Guy Motors had done.

    The experience of welding the prototype A10E1 tank had thrown up a number of problems and the team from Vickers were keen to see how the Wolverhampton company had resolved them. The tour of the factory coincided with the completion of one of the Wheeled Tanks. They were walked through the entire process and Carden was impressed with the way both the management and workers were happy to share their expertise and experience. If war came, as it seemed more and more likely, this kind of sharing of ideas and openness would be highly valued.

    The Vickers-Armstrong board of directors had been aware for some time, when looking at how the War Office were involving so many other companies in the manufacture of tanks, that the companies being chosen tended to be engineering firms that had less than full order books. The really successful engineering firms were so busy with their civilian orders that they had no spare capacity for military orders. The reason that companies like Vulcan Foundry and some of the locomotive manufacturers had spare capacity was that they hadn’t modernised their plant or working practises. The way the A12 was designed was a case in point, it was extremely slow to build because it tended to use outdated, but highly skilled methods.

    With Vulcan Foundry as the ‘parent firm’ a number of other companies were making sub-assemblies, so that large pieces of tanks, like hulls or turrets, were having to moved from one part of the country to another, before final assembly. Since standardisation wasn’t something that these companies were well versed in, the ‘craftsmanship’ of fitting together two pieces that didn’t fit was necessary. All of this was highly inefficient. What made it worse was it was hampered all too often by the lack of quality control, all of which meant that a tank might take too long to build, be unreliable, heavier than it needed to be, and more expensive.

    What Guy Motors had shown with the Wheeled Tank, which they called the Ant, was a company that had evolved and had therefore produced a vehicle for the army that was all the better for the new techniques. When looking at improving the tank shop at Chertsey, the Vickers team were taking notes of some of Guy Motor’s systems. Getting to see the Ant up close gave Carden a feeling that his decision to press for the Valiant to be a completely welded tank was along the right tracks. The up-front investment in a new factory, training of new employees and the specialised equipment for welding would be expensive. What Carden firmly believed, and the Board of Directors needed to be persuaded of, was that the investment wouldn’t just be good for the company, it would be good for the country.

    The problems that Vickers Armstrong had experienced with building the welded A10E1 were similar to the problems that Guy Motors had had to resolve, and the Vickers team were impressed by their solutions. There was obviously going to be differences between welding the light tank armour of 14mm to the much thicker armour planned for the Valiant. The Guy Motors methodology however was applicable even to the heavier armour plate, they were even prepared to made a demonstration for their visitors.

    This was the final piece of the puzzle, and the report given to the Board of Directors about the visit to Wolverhampton pressed for Chertsey tank shop improvements to have welding as its primary method of tank manufacture. There would also have to be a further expansion of the associated steel works to meet demand for armour plate. Eventually Elswick would be able to follow the move to welding, and with all the Shadow Factories being built for the RAF, the War Office would probably be persuaded to repeat what they had done at Elswick. In that case Vickers Armstrong met 40% of the costs of the improvements to the tank shop, the War Office met the other 60%. It was also proposed that the Chertsey site should be big enough for the expected increase in orders for tanks should war break out. The ability to build 100-120 tanks per month that seemed ludicrous just last year, was looking more and more necessary.
     
    9 May 1939. London, England.
  • 9 May 1939. London, England.

    With Giffard Martel having been promoted and given command of the 50th (Northumbrian) Division, he had been replaced by Brigadier John Crawford, who had been one of Martel’s Assistant Deputy Directors of Mechanisation.

    Crawford joined the meeting in the office of the Director of Mechanisation, Major-General Alexander Davidson. The meeting was to discuss future orders for cruiser tanks. The requirement for cruisers had risen substantially to 1285. 262 were requested for the rapidly expanding Territorial Army to supplement the forty-two they had been promised for training. Since the Mobile Division was to be replaced with two Armoured Divisions, their requirement meant there was a need for many more cruiser tanks.

    Using the distinction between the light and heavy cruisers continued to cause problems, as only Vickers’ A10 could be considered in the heavy category, and there were some at the meeting who were unhappy with Vickers decision not to change the design to take a hull mounted machine gun. Each Division would have a Light and a Heavy Brigade, so 435 Heavies were needed, but orders had only been given for 160 A10 (Cruiser Mark II). There had been orders for 420 light cruisers made out of the requirement for 852. The orders made so far were for 125 A9 (Cruiser Mark I), 65 A13 (Cruiser Mark III), 130 A13 Mark II (Cruiser Mark IV) and 100 for the paper design of the A13 Mark III (Cruiser Mark V Covenanter*) ‘from the drawing board’. That left the need for another 432 Light and 275 Heavy Cruisers.

    Both London Midland Scottish and Nuffield’s had been working on heavy cruiser designs under the specifications A14 and A16 respectfully. The LMS A14E1 wasn’t running yet, it wasn’t expected until June at the earliest, but at the last visit it already looked as if was going to weigh more than five tons in excess of the 24 ton limit it had been set at, even though the armour was only just over an inch at its thickest. Part of the problem was the new form of the Wilson steering which offered a choice of seven speeds for each track. It was extremely complicated and had a weight penalty, but it was considered an improvement on skid steering because it didn’t waste power.

    Nuffield’s A16, like LMS’ A14 also was designed with two forward machine gun turrets in addition to the main turret’s co-axial MG and 2-pdr. It was expected to be delivered to the MEE at Farnborough in a week or so. Major-General Davidson had never been terribly keen on the A16. Since Crawford had replaced Martel, some of Martel’s particular pet projects were falling out of favour, including the A16, which had been dogged by problems due to changes to various specifications. In the judgement of Davidson as Director of Mechanisation the A16 wasn’t going to be a practical proposition for volume production as it would be prohibitively expensive and its weight would lower its manufacturing output. It also looked like the Liberty engine would struggle to deal with the weight of the design.

    In the meantime, LMS had been working on the A13 Mark III (Covenanter*), whose low silhouette and greater speed was considered more advantageous than the A14 specification and already 100 of these had been ordered without requiring a pilot model. At the same time Nuffield had been working on what some at the meeting called the A13 Mark IV (Crusader*), though it had also been given the reissued A15 specification. Since this would be some five tons lighter than the A16, it was possible to increase the armour basis to one and a half inchs (40mm) on the turret and one inch (30mm) on the hull. This would add a ton to the weight and reduce the maximum speed from 31 to 28mph. At this point General Davidson remarked that this came very close to the original 1938 specification for the A14 and A16. Brigadier Laurence Carr, Director of Staff Duties, wondered if this realistically wasn’t just another Light Cruiser, but considering the circumstances it would have to be used in the heavy cruiser role.

    Davidson therefore proposed ordering four hundred cruisers, preferably 200 Mark IVs (Crusader*) and another 200 Mark IIIs (Covenanter*). The Mark III was certainly the inferior of the two, but a great deal of its design work had already been completed and so production could begin sooner. Another one hundred would be ordered from which ever of the models could bring in new firms as sources of production.

    Carr’s deputy at SD7 branch, the office responsible for the equipment and organisation of the armoured forces, was Brigadier Frederick Hotblack who had spent a couple of years in Germany as Military Attaché. As Deputy Director of Staff Duties, Hotblack had been impressed with the Valiant’s specification, it was already better protected than the proposed A13 Mark IV, and although slower, it wasn’t anything like the Vulcan’s A12 speed. If Nuffield’s Mark IV was coming in at 28mph, the Valiant was only five miles per hour slower. The Valiant was also much further forward, at best Nuffield wouldn’t be able to produce their tank for service until Spring 1941, while the Valiant would be in production in Spring 1940. During his time in Germany he’d got a real sense of the way the Nazis were going about their rearmament and Hitler’s designs for Lebensraum. He had come to the conclusion that the British army would need to speed up its preparations for war. He was also of the opinion that a bird in the hand was worth two in the bush.

    The other thing that convinced Hotblack about the value of the Valiant was that he had befriended a few officers in the Panzwerwaffe of the Wehrmacht. They had looked at the same results of the Experimental Mechanical Force exercises but had drawn different conclusions from the British. The Panzer Divisions were combined arms units, with two panzer regiments, a motorised Infantry Brigade, reconnaissance battalion, motorised artillery and ancillary support all combined in an integrated force. In comparison the new 1st Armoured Division was tank heavy, its Support Group of infantry with anti-tank and anti-aircraft guns, were just enough to protect the tanks when they were laagered up. He didn’t know a great deal about the latest German tanks, but he was sure that the way they were heading from the Panzer I and II was that they were working on what the British called Medium tanks.

    It seemed to Hotblack that both the proposed cruiser tanks weren’t much of an improvement on the A13, especially the Mark II with the same 1.1 inch armour and 2-pdr gun. The LMS Mark III looked very smart and fast but Hotblack considered it a dead end. There didn’t seem to be any room for improvement in armour or weaponry. The Nuffield Mark IV looked a bit better, but Hotblack wasn’t quite so sure that the timetable that the company was proposing was realistic. From design to service in two years would be a stretch. From what he was hearing about the various parts of the design other than the Christie suspension, the Meadows engine, and Wilson steering weren’t fully worked up. Without pilot models to work through some of the problems, the chances were that once the tanks entered into service they would probably be unreliable.

    On the other hand, the Vicker’s Valiant was a good tank, and with room for improvement. If an extra 400 of these were ordered instead of the two cruiser types, they would be in service faster and be more capable from the get go. A Tank Brigade made up of Valiants, working in conjunction with a Motorised Infantry Division would be a far more effective military force, going back to his experience with the Tank Corps in 1918. His however, was a voice crying in the wilderness it seemed. Cruiser tanks was what a British Armoured Division needed and Cruiser tanks was what they would get. The Infantry tanks in Tank Brigades were all well and good, but an Armoured Division had a mission, and that mission needed fast tanks, faster than the Valiant at least.

    (*names given subsequently as Covenanter and Crusader are not yet actually used here)
     
    Last edited:
    5 June 1939. Chertsey, England.
  • 5 June 1939. Chertsey, England.

    One of the most common criticisms that had come back to the Vickers Armstrong design team from the production models of the A9 and A11(Matilda) in service use was the tracks. Generally, the tracks used on previous Vickers tanks were all relatively simple and since the tanks all tended to be fairly light there weren’t any great complaints. The weights of the A9, A10, A11 (Matilda) and Valiant were much higher and the ‘lubricated’ system had proven unwelcome by the Army.

    The tests that had been done on the Czech built TNH/P tank had universally been positive about the tracks. A number of tests and inquiries had been made on them and the results were back. The steel used on these tracks had a notable Manganese element in the alloy, not dissimilar to that used in British railway tracks. The addition of the manganese to the steel provided greater durability. When the design team read the reports, they began to wonder why they’d never thought of it, it seemed so obvious.

    Ordering the new alloy steel was straightforward, there were plenty of steel mills producing that kind of steel. Once the durability was sorted, the next step would be sort out the best means of linking the track shoes together, so that their durability would be enhanced by ease of use. While there was some resistance towards what could be described as corporate espionage, the track system on the TNH/P tank seemed a pretty good place to start looking for a solution. The work would take a couple of months, but it was hoped to have the new track ready for the first production A10 which was due to be completed in November and the Valiants in the new year. In the meantime, there were enough prototypes available to test the new tracks in advance and if these trials were successful then replacements could be sent out to the existing A9 and A11 users.
     
    21 June 1939. London, England.
  • 21 June 1939. London, England.

    Commander Robert Micklem had taken over the role of managing the tank arm of Vickers Armstrong from Sir Noel Birch after his untimely death earlier in the year. Along with John Carden and Leslie Little they were attending a meeting in Vice-Admiral Harold Brown’s room at the War Office. In his role as Director General of Munitions production, the meeting had included all the usual people involved in dealing with Tank Types and Production. Maurice Taylor, Brown’s deputy was at the meeting; as were General Ronald Adam, the Deputy Chief of the Imperial General Staff; Laurence Carr and Fredrick Hotblack from the Director of Staff Duties; Alexander Davidson and John Crawford as Director of Mechanisation and his deputy.

    This particular meeting was concerned with Vickers’ contribution to the effort to get tanks into the hands of the army. Over the last week orders had been made for more A13 Mark IIs, bringing the total order of Mark I and IIs up to 225. Nuffield’s A15, now to be built without the Wilson steering units and replacing the Meadows engine with their own Liberty and constant mesh gear box, had received an initial production run of 100 straight from the drawing board.

    The War Office had requested that Vickers look at developing a larger version of their A17, or Mark VII light tank, which had the Vickers codename Purdah to be used as a light Cruiser. The specification A18 had been given to it, but Leslie Little who had done the work on the A17, explained that the A18 couldn’t be made without a pilot model because it contained a number of new features that couldn’t be accepted without a proper trial. In that case it wouldn’t be producible until 1942. This, the meeting concluded, ruled it out of the present program, though General Ronald Adam (DCIGS) expressed the view that the chassis alone should be proceeded with, to give enough information about the new type of steering, irrespective of what fighting body would be fitted later. Since Vickers had been looking at the A17 as a basis for some kind of armoured carrier for soldiers they were happy to do so.

    Now that the Cabinet had agreed that organisation for war in Europe was the main task of the army, Adam noted that Germany and Russia were now fielding ‘heavy Cruiser tanks armed with short field guns, anti-tank guns and several machine guns.’ When pressed, Adam noted these to be the Soviet T-28 and the German Panzerkampfwagon III and IV. British doctrine considered the Cruiser tank to be essential for countering hostile tank formations. Therefore, Adams noted that it was important that the Armoured Divisions replaced their machine gun armed light tanks with 2-pdr gun armed Cruisers as soon as possible. The Divisional Cavalry Regiments, the reconnaissance element of the infantry divisions, would likely require light tanks for some time to come, and more of these Regiments could receive the light tanks being replaced by Cruisers in the Armoured Divisions.

    What Adams remarked was as a balance to the superior numbers and more powerful types of potential enemy tanks, the British army led in the art of shooting on the move. It was an important part of the design for tanks for the army that the tank should be a good gun platform. The tests being done on the A13 were producing very good results, and it was hoped that the later marks (III and IV *Covenanter and Crusader) would be the same.

    The fact that there were far fewer tanks being produced than were required put the War Office into something of a bind. There would normally be a war reserve to provide replacement tanks. The estimated war wastage rate, normally counted at 18% for Infantry tanks and 14% for Cruisers, would mean that the war reserve would have to have enough tanks to replace casualties at that rate. The Deputy Chief of the Imperial General Staff admitted that the General Staff would rather have fewer tanks as replacements and in reserve, if there were no other way out, than produce tanks below the level which they thought necessary to enable them to engage hostile tanks with a fair prospect of success. In other words, the General Staff preferred to build up the field force at the expense of the war reserve.

    Harold Brown, from his perspective of overseeing munitions production, pointed out that everybody was competing for requirements. The army wasn’t just looking for tanks, but for other vehicles, guns, engineering stores, and the Air Ministry had already cornered a lot of the best engineering resources in the country. The availability of trained labour was deficient in the country too. Currently, other than Vickers, there were five firms engaged to manufacture Cruisers (Nuffield, LMS, Harland & Wolff, Metro-Cammell and BRC&W). With the current orders already made these would complete their orders during the early part of 1941. At most, all these companies combined, would only be capable of producing just over 200 extra tanks up to August 1941 with the current allocated budget.

    At this point Commander Robert Micklem reminded those present at the meeting that Vickers, unlike the five firms which had just begun manufacturing tanks, was the only place, other than the Woolwich Arsenal, with both the experience and capability to meeting the army’s needs. The downgrading of the A9 and A10 Cruisers to ‘stopgap’ status had left the Army with a wide gap between its orders and when they would be in service. The A13 Mark I and II, were in the opinion of Carden and Little were reasonable Cruiser tanks, especially the Mark II with an inch of armour. The Mark III designed by LMS looked to Carden like it would suffer from cooling issues, the radiators were separated from the engine by the fighting compartment, and he couldn’t see how that would work, especially if, according to the designs he had seen, the air cleaners were external. He hadn’t seen much of Nuffield’s A15, the Mark IV of the A13, but since they had reverted back to the Liberty engine and constant mesh gearbox, both Cardel and Little were worried that it too would suffer from mechanical unreliability. Over the years Vickers had learned that durability was important in designing tanks, there was no point in having a lot of tanks being down for maintenance when they were really needed out in the field.

    There was talk of trying to bring Leyland Motors into the tank business, and the Vickers team had heard that the War Office was paying for the building of a new factory for Leyland, equipped with an overhead crane, to allow the manufacture of tanks. Meanwhile Vickers had set aside funds to complete the work that had been started on a new tank shop at Chertsey to supplement Elswick Works which was already producing the tanks the army needed. The order for 180 A11 infantry tank was well on the way to completion, and since Harland & Wolff and Metro-Cammell were building the majority of the A9 and A10 orders, Vickers would be in a position to increase production of the Valiant over and above what had already been ordered. While it had been designated as Infantry Tank Mark III, Carden and the rest of the Vickers team firmly believed that it was entirely suitable for the heavy cruiser role.

    Once more Frederick Hotblack, the Deputy Director of Staff Duties, spoke up in favour of this, and to the surprise of some, so did General Alexander Davidson. Since the meeting of this group responsible for tank types and production in May, Davidson, with his deputy Brigadier John Crawford, had gone back over the MEE report on the Valiant prototype and compared it to the proposed A15 from Nuffield. The fact that in the meantime Nuffield had changed their proposal from the Meadows engine and Wilson Steering to their own Liberty engine and drive and gearing system, made the War Office’s desire for the A13 Mark III and Mark IV (*Covenanter and Crusader) to share as many components in common as possible, mute. Two off the drawing board designs, neither of which would have a pilot model, was a recipe for delay and disappointment.

    The Valiant however, in the eyes of Laurence Carr, Hotblack’s superior, didn’t fit the Cruiser role, for two reasons. It was much heavier than the 18-ton limit of the bridging equipment which would be assigned to the Armoured Division, and, although fast for an Infantry tank, it just wouldn’t keep up with the A13 Cruisers. The slower speed of the A9 and A10 was why they had been relegated to ‘stop-gap’ tanks. The same problem applied to the Valiant, it was a very good Infantry tank, but it couldn’t be called a Cruiser, even a heavy Cruiser. Carr also expressed his dislike of the Valiant being powered by a diesel engine, as all the Cruisers in the Armoured Division would be petrol engines, it would complicate the Divisions’ logistics.

    The Vickers team, in that case, were prepared to offer a variant of the Valiant tank with the petrol Napier Lion aero-engine rather than the Ricardo diesel version of the engine. They would also shave off a little armour plating from non-critical areas to bring down the weight by about a ton or two. They would call this the Valiant Mark I*, and the Infantry Tank Mark III would simply be the Valiant Mark I. Their calculations were that this would probably give the tank a few extra miles per hour (around 26-27mph on the road) at the cost of a slightly more limited radius of action, petrol being less economical than diesel. Because Vickers had bought up the total ex-RAF stock of Napier engines and their spares, with the right investment, they could make up the army’s shortfall of 220 Cruiser tanks even before Nuffield and LMS could get their Mark III and IV up and running.

    Robert Micklem also noted that should war break out, the current budget from the Treasury was likely to go out the window, and the already desperate need for tanks would be multiplied exponentially. Giving Vickers an order for 220 tanks now, and agreeing to share in the investment costs at Chertsey to expand its capacity, would provide the 1st Armoured Division a heavy Cruiser better than anyone else was fielding. The cost per tanks of the petrol version of the Valiant would slightly cheaper as the engine wouldn’t need to be converted to the diesel version, and as war seemed inevitable, the cost of a tank would soon be much less of a worry to the Treasure than it was currently.

    The Vickers team were asked to leave the meeting at this point so that the War Office team could discuss the proposal. The problem boiled to down to the designation of tanks between Light, Cruisers and Infantry types. Specifically, what was the difference between a heavy Cruiser and an Infantry tank when their armament was the same. The difference in weight was one thing, the standard class 18 bridge used by the Royal Engineers limited the weight of tanks to 18 tons. This had already been superseded by the A12 and Valiant, so that a Class 24 bridge had been developed, though it was able to cross shorter gaps than the Class 18. Although Nuffield had been told in no uncertain terms that the A15 had to be less than 18 tons, because it had been ordered off the drawing board, there was no guarantee that it wouldn’t in fact be heavier. The difference in speed was the other factor. The A15 was planned to be in the 27-28mph bracket, a few miles per hour slower than the A13 Marks I, II and III. The Vickers team said that petrol Valiant would be around 25-26mph. For a heavy Cruiser, considering the only other tank fitting that description was the A10, which could only muster 16mph, a top speed in the mid-twenties was very attractive.

    John Crawford remarked that the Vickers team had already designed the Valiant with being able to fit a bigger gun in the turret and take on more armour in the future made it a better bet than either LMS’s A13 Mark III, which had almost no room for improvement, or Nuffield’s A13 Mark IV, whose ability to be improved was going to be limited now by the Liberty engine. Frederick Hotblack agreed with that assessment, and noted that Vickers had the experience and expertise to get the Valiant into production quicker and it probably being more reliable from the outset than the untested Nuffield Mechanisation and Aero Ltd product. If the proposed tank factory being built for Leyland was put under the parentage of Vickers, and the improvements to Chertsey were agreed, then the program to augment the war potential would be with a company that had a proven track record of actually designing and building tanks, unlike all the other companies used so far.

    What finally convinced the meeting of the Tank Types and Production was the speed at which Vickers promised they would be able to produce the tanks. With expanded facilities, including Leyland’s new factory, once they had completed the A9, A10 and A11 orders, Vickers could manufacture both the Valiant Mark I and Mark I* at a minimum of forty units per month, far more than either Nuffield or LMS could match. With Harland & Wolff, Birmingham Railway Carriage & Wagon Company and Metro-Cammell already building Vickers designed A9 and A10s, they too could move on to building the Valiant once they’d completed their current orders, should the need for even more tanks be necessary.

    When the Vickers team were readmitted to the meeting, Vice-Admiral Harold Brown shook hands with Robert Micklem for 220 Valiant Mark 1* which would be confirmed by letter in the following days. This would be in addition to the 275 Valiant Mark I that would be needed by the Tank Brigades to supplement the numbers of Vulcan Foundry’s A12 which were still were a few months away from initial delivery. The Vickers team was delighted, the delay in receiving any orders for the Valiant had been affecting their planning, 495 tanks was by far the biggest order in the company’s history. Carden was a little disappointed that he’d had to compromise on the Mark 1* variant, but his guess was that when war broke out, the army would see that the diesel version was the better choice.

    The other question that Leslie Little wanted to ask was something that had been bothering him about the order for 120 A17 Purdah, Mark VII light tanks which he was overseeing. Most of these were to be built by Metro-Cammell, but there was a distinct possibility that with all the extra orders for tanks that were being made, that the QF 2-pdr was likely to become a bottleneck. Woolwich Arsenal were being asked to produce enough of these in the towed carriage version for the anti-tank regiments of the Royal Artillery, and now Vickers would need 500 more on top of LMS and Nuffield’s requirements for the various A13 marks. With Vickers own 2-pdr pompom being used in the A11s, was it feasible to offer the same gun in the A17 or either of the Valiant variants if Woolwich was unable to meet the demands of all the extra tanks being ordered.

    Everyone in the War Office knew that the Director of Artillery, Major-General E M C Clarke, was furious that the Vickers pompom had been selected for the A11. No one was entirely sure why, but he seemed to have a fixation against using any of Vickers designed guns. Obviously, there was a degree of protecting the gun design team at Woolwich from the competition, but Vice-Admiral Brown knew that even suggesting using anything other than the QF 2-pdr would send Clarke into apoplexy. When Sir John Carden noted that Vickers was looking at an alternative to the Close Support 3.7-inch howitzer, something that would be better than either the Soviet 76.2mm gun on their T-28 or the short barrelled 75mm on the Panzer IV. Vickers had experience of making both these calibres of cannons, but the potential for conflict with Woolwich became crystal clear.

    Woolwich was working on a 3-inch howitzer to replace the 3.7-inch Close Support gun. They were attempting to build it in such a way so that it could go into the same mounting on a tank used by the QF 2-pdr, simplifying production of the two versions of the tanks. The idea that Vickers might be developing something in parallel would probably give General Clarke palpitations. At this point Carden thought it was probably better not to mention that what they were looking at wasn’t just something that could throw smoke shells, but something that could also penetrate the armour of a tank as well armoured as the Valiant.

    The Royal Tank Corps’ opinion of the A11’s pompom gun was very positive. Putting into a light tank like the A17 would be interesting, but there was just no way Clarke would allow it in a Cruiser tank. When the orders for the Valiant Mark I and I* arrived in Vickers headquarters, a percentage of the tanks to be produced were, as usual, to be in the Close Support variant, using the 3.7-inch howitzer, as the 3-inch weapon wouldn’t be ready in time. The co-axial machine gun was to be the BESA air-cooled weapon, which were expected to be ready by the time the Valiant would go into full production.
     
    28 June 1939. Shoreham-by-Sea, England.
  • 28 June 1939. Shoreham-by-Sea, England.

    Sir John Carden had come back to Ricardo Consulting Engineers to talk about engines. The contract for almost five hundred Valiants meant that the entire stock of Lion engines was going to be used up, so an alternative would need to be found, and soon. Once again, the options available were limited. The preferred Rolls Royce Kestrel wasn’t available because the Air Ministry already had contracts for just about everything Rolls-Royce could produce. It was the same story with all of Bristol’s engines, and since many of these were radial engines, they weren’t really suitable in the first place. Other manufacturers of aero-engines: Fairey, Armstrong-Siddeley, Napier, De Haviland etc were all likely to be in the same boat. Either the Air Ministry had first dibs on their engines or they were unsuitable to be used in tanks.

    Vulcan Foundry’s A12 was using the double mounted AEC diesel, Nuffield’s had gone with their own Liberty for their A13s and LMS were going to use a Meadows V12 in the A13 Mark III. None of them provided the kind of power and durability that Carden knew would be essential for the Valiant. Ricardo had continued working with Napier as they were trying to get their new Sabre engine up and running. The Air Ministry were putting a lot of hopes into this engine to be used in the Hawker Typhoon, the proposed successor to the Hawker Hurricane. Since the company’s design team were going all out to make this successful, the idea that they might do something on the off chance that the War Office might look for something in the future was unlikely. Ricardo also noted that his impression of the firm didn’t fill him with any great confidence that they would be able to successfully manufacture the large quantities of the Sabre engine. Having looked at the Rapier and the Dagger, the Sabre would likely suffer from the same build-quality problems.

    Carden asked about the Culverin, Napier’s license-built version of the Junkers Jumo 205 diesel. As before, Ricardo wasn’t impressed by it. In his last visit to Acton, Napier’s factory, he had been shown the E109 engine, which was half of a Sabre, with 12-cylinders and a single crankshaft which displaced 1,119 cu in (18.34 L). The original diesel engine Napier had worked on, the E101 had been abandoned around 1933, with only two- and six-cylinder test engines having been built to test the sleeve-drive mechanism which would prove the validity of the design. The new aircraft engine, designed mostly by Napier’s Frank Halford, for a 24-cylinder, H-configuration engine capable of 2,000 hp (1,491 kW) engine was given the Napier designation E107 and became known as the Sabre. Halford had used the E101 diesel as a basis at least in part for the new engine. Ricardo thought he could probably do something with the E109, but again they were going to be limited by time and the ability to get it mass produced by a company which wasn’t already overburdened by rearmament orders.

    That brought them to firms making engines for either use in lorries and cars. AEC’s diesels being used in Vulcan’s A12 had been developed with Ricardo’s help. Due to high tax on lorry engines designed to carry more than 2½ tons, to try and shore up the railways share of the freight market, not many companies had been working on big diesel engines. Meadows of Wolverhampton and Vauxhall’s Bedford range were probably the best of the big petrol engines around. Both Ricardo and Carden weren’t convinced that either of these were going to be the solution to their problems. Which brought them to diesel manufacturers.

    Thornycroft’s RY 12 had been used in the A6E3 prototype, also it had been looked at for the A14 and A19 specifications, neither of which had come to pass. Ricardo had worked with Thornycroft to offer a shortened version of the RY12, but the then Director of Mechanisation, Giffard Martel, had been quoted as saying about it that he was ‘being asked to buy a pig in a poke.’ Ricardo was more positive about it, but Thornycroft weren’t set up to make big quantities of engines, so Vickers would probably struggle to get the kind of numbers they needed in a timely manner.

    Another big diesel company was Paxman, again a company that Ricardo knew well and had worked with. Generally, their engines, designed for the marine environment, tended to be bigger and heavier, but he did speak favourably about the VEE RB 12-cylinder engine, which had room to be developed into something lighter than the current 7600lbs. Carden remarked that ‘land-ships’ were something that harkened back to the Great War. The advantage of aero-engines was they were designed to be lighter from the outset, the Napier Lion weighed just 960lbs in comparison. That was the light-bulb moment for Carden.

    Ricardo Consulting Engineers had produced an excellent diesel engine for tanks from the Napier Lion. What they had didn’t have to be replaced with something else, they just needed the capacity to persuade Napier to license the manufacture of the Lion, perhaps allowing the Sea Lion line they had to be taken over and expanded by another firm. A firm with the capacity for expansion, but one with enough experience of mass production, to make the diesel, and indeed, if necessary, the petrol version of the engine. There were various companies such as Leyland and Rootes which they talked about and dismissed. The one they kept coming back to was Perkins. It was a relatively new company, one that had been starved of investment, yet their P6 was a very good diesel engine, and it looked as if it was going to be a commercial success, building on their previous Lynx and Leopard engines.

    If Perkins could be approached now, with Vickers’ investment, Perkins would be in a position to offer an excellent choice of various powered diesel engines. This wouldn’t just be for tanks, but any other rearmament role that the Air Ministry, Admiralty or War Office required. It would probably take a year to get the production line up and running, which would be just in time to be available when the current Lion engines were already fitted into Valiant tanks.

    Ricardo raised the possibility that Perkins may not want the kind of investment that Carden was talking about. The threatening clouds of war were getting darker by the day, and Carden was convinced that every sinew of British industry was going to need to be stretched when it was finally declared. Perkins’ P6 was already proving a good engine. With companies like Commer that used it winning larger and larger orders for the army, there was no doubt that the national requirement for the P6 would go through the roof. With Vickers help now, and the possibility of War Office funds being added, then Perkins, making the P6 and the Lion, would be a position to really thrive. They were also a young enough and innovative company that would take to modern techniques of manufacture like a duck to water.

    The other advantage that Carden could see was that Charles Chapman, the designer of the P6, given the Ricardo diesel Lion to work on, would be able to simplify the design for mass production. Ricardo did agree that Chapman was a very good designer, and given it was entirely possible that he could take the diesel engine to a new level of sophistication and power. All of this would increase the chances that the newly built Lions would have a much better build quality, and be able to be improved over time. In some ways it was a bit of a longshot, but short of any other ideas, like steam engines, it seemed like something worth investigating.
     
    Last edited:
    Status
    Not open for further replies.
    Top